Saturday, November 20, 2010

Learning Football Books

Building Diary: Day 48 - still 28 days to opening!!

And again a week ago. It has again Allerhand done
  • the windows are now all mounted
  • the plastering in the interior have been completed
  • the roof was
  • was extended, the roofing work began
  • the crane removed
  • various containers were already being picked up again
  • the excavator has finished outside the system - creating a beautiful lawn in the spa :-)
  • the Vorabeiten have begun for the screed

Construction Week 7 is almost over


the excavator makes the beautiful outdoor facility - in the summer, we look forward to a beautiful lawn

the windows are mounted - the crane has been dismantled
have started the roofing work

the roof was extended
expansion of 6 rooms to suites - this will create the new living area with comfortable couch

views from the suites to Gosaukamm with today easily concealed miter

expansion of 6 rooms to suites
construction day 48 - still 28 days for the opening on 18 December 2010

the new conservatory is nearly complete - lacking only the finishing touches

also to our employees we thought - a new staff room :-)

Construction Week 7 is over - Does so not so bad, right?


HOLIDAYS ALPENGASTHOF Laemmerhof
in the holiday LAMMERTAL-Dachstein West
from 18 December 2010 - www.laemmerhof.at Eröffnunung with new wellness area
Hotel basic